Technical maintenance for facilities: what an HVAC and MEP contract covers

A technical maintenance contract is bought per asset, not per person. That one difference from housekeeping explains most of what goes wrong with hard services: the scope is invisible until something breaks, the price is built on a plant list the buyer has never seen, and “comprehensive” turns out to describe a cap on spares rather than a scope.

The buyer’s guide to facility management services in India covers the whole contract and what integrated facility management is explains how the two halves fit together. This post is the hard-services half: what the scope includes, which inspections the law runs on its own schedule, who pays for a compressor, and how the monthly value is assembled.

Key takeaways

  • Cooling equipment is where the money and the risk sit: chillers account for more than 40% of the energy used in commercial buildings (Ministry of Power, 14 September 2018), and India’s cooling demand is projected to rise about eight-fold between 2018 and 2037-38 (India Cooling Action Plan, 2019).
  • Chiller efficiency is now a label, not a claim: water-cooled and air-cooled chillers moved into BEE’s mandatory star-labelling regime on 1 January 2024 (notifications S.O. 4088(E) and 4089(E), 18 September 2023), so IS 16590 test data exists for the machine you are maintaining.
  • The statutory floor moved on 21 November 2025. The Occupational Safety, Health and Working Conditions Code replaced the Factories Act, and lifts, lifting tackle and pressure plant now sit in its Second Schedule, so the inspection interval comes from central or state OSH rules rather than the old Act.
  • The law’s evidence runs on its own clock: an annual boiler certificate (Boilers Act, section 8), a lift licence under the state lift Act, fire alarm upkeep under IS 2189:2026, and periodic inspection of the electrical installation under the CEA safety regulations.
  • No new HCFC equipment may be manufactured in India since 1 January 2025, so an R-22 or R-123 chiller now depends on a servicing allowance that shrinks to a full phase-out in 2030. Refrigerant availability belongs in the replacement plan, not the maintenance budget.
  • In the worked example below, the roster and its statutory load are 64% of the contract value and the spares provision is 16%. A quote without that second line is 17% cheaper and will be argued about by month seven.

What “technical maintenance” actually covers

MEP means mechanical, electrical and plumbing; MEPF adds fire. The letters describe disciplines, not a scope. A scope names systems, and for each system it names a boundary: what the routine visit touches, what the specialist subcontractor owns, and what is a capital repair.

System Routine maintenance covers Specialist or statutory A skipped task looks like
HVAC Chiller logs, AHU filters and belts, coil cleaning, pumps and cooling towers, water treatment, setpoints Chiller overhaul and refrigerant work, OEM controls, duct cleaning Rising condenser approach, comfort complaints, a compressor that fails in May
Electrical HT and LT panels, transformers, DG and UPS, earthing, lighting, load logging Transformer oil testing, relay calibration, thermography, statutory inspection A hot joint that trips a floor, a DG that will not take load
Plumbing and water Pumps, sumps, domestic water, drainage, STP operation, water quality Effluent testing, consent compliance, tank cleaning to state rules A leaking riser, a sump that overflows in the monsoon, an STP notice
Fire Panel checks, detector and call point tests, hydrant and sprinkler upkeep, extinguishers Fire NOC compliance, Form B or its state equivalent, refills A panel in bypass, a pump that does not start on test
Lifts and escalators Rider complaints, housekeeping, coordination with the OEM OEM maintenance, statutory inspection and licence under state law An entrapment, an expired licence found at renewal
ELV and BMS CCTV, access control, PA, BMS points, alarms and integration Cyber hygiene, software versions, control-system changes Alarms nobody reads, a BMS reporting a plant that is off

Two boundaries cause most of the arguments. Fire detection often sits with security because the panel is in the lobby, while suppression sits with MEP. The BMS is the only place where the chiller, the panel, the lift and the fire panel meet. Neither split is wrong; both need to be written down.

Four contracts hide inside the word “AMC”

An annual maintenance contract is not one product. There are four, plus the in-house team you are usually comparing them against, and the difference between them is who carries the risk that the asset is worse than expected.

Shape Included Who pays for spares Price basis Where it fits
OEM AMC Manufacturer’s PPM, diagnostics and parts Usually the owner, at OEM list price Per asset, per year Equipment in warranty, or plant only the OEM can service
Comprehensive AMC PPM, labour, breakdown attendance, named spares The provider, up to a cap and an exclusion list Per asset, per year Sites with a plant list and a condition baseline
Non-comprehensive AMC PPM and labour; parts billed as used The owner Per asset or per visit New buildings with warranty cover, or central spares
Breakdown or time-and-material Attendance when called, no schedule The owner Per call, plus parts and hourly rates Small sites, standby plant, a gap between contracts
In-house team Your technicians, tools and stores You Payroll plus statutory Large campuses with critical, continuous plant

“Comprehensive” is a statement about spares, not about scope. Two comprehensive quotes can differ by a third because one includes chiller overhauls and the other excludes “major repairs”, a phrase with no boundary. Read the exclusion list first and the price second; the pricing model comparison sets the shapes side by side and how pricing works explains a credible build-up.

One question separates competent bidders from the rest: does the price include a named emergency response, or only attendance “on call”? A chiller trip at 2am is not a ticketing event.

The asset register is the scope document

You cannot price hard services without a plant list, and most buyers do not have one. What exists is a set of warranties in a drawer, a single-line diagram from commissioning, and a technician who knows which pump is temperamental.

Eight fields per asset make a register a buyer can tender against:

  • Identity — make, model, serial number and year installed.
  • Capacity — TR, kVA, kW, litres per second or KLD.
  • Location — specific enough that a new technician finds it.
  • Refrigerant or medium — because it decides what replacement costs.
  • Criticality — against the consequence of failure, not the price of the machine.
  • Condition — a dated observation, not a word.
  • Warranty and OEM status — including when the last overhaul happened.
  • Statutory status — licence or certificate, with its expiry date.

Criticality is what turns a register into response clocks. The KPI and SLA guide explains why response, restoration and resolution are three different clocks; the register decides which assets get the shortest one.

Tier Test Response expectation
A Failure stops the business, breaches a licence, or endangers people: chillers, HT panel, fire pumps, lifts, STP Attended on the same shift, worked continuously, escalated to a named manager
B Failure degrades comfort or a service level within a day: AHUs, domestic pumps, BMS, lighting circuits Attended within the day, restored the next working day
C Cosmetic, or a manual workaround exists: a fan coil in a store, a spare pump, external lighting Scheduled into the next cycle

The register is also the honest place to record what you do not know. A quote built on an incomplete register is not wrong; it is priced for the risk of the missing half, and the buyer pays for that risk in the fee or in the first invoice after a breakdown.

The preventive calendar: what has to happen, and how often

A preventive maintenance plan (PPM) is a task list with dates, owners and measurements. Without the measurement it is a visit record, and the difference shows up in the annual review. This is a starter calendar for a mid-size commercial building; the OEM manual and the governing standard set the actual intervals.

Cadence HVAC Electrical Plumbing and water Fire
Daily Chilled water and condenser temperatures, approach, amps, noise; AHU status Panel load and temperature; DG log; UPS alarms Pump pressures, leaks, sump levels; STP dissolved oxygen and sludge Panel showing normal, no fault outstanding
Weekly AHU filter differential pressure, belt tension, drain pans; tower blowdown DG no-load run; battery voltages Strainer cleaning; water meter Review the week’s events and confirm each was handled
Monthly Coil condition, grease and alignment, vibration check DG on load; termination torque; lighting survey Water quality spot test; sludge wasting Hydrant and sprinkler visual; extinguisher checks
Quarterly Water treatment panel, valve and actuator stroke, control sequence Thermography of panels under load Sump and tank inspection; drainage rodding Trigger device in each zone, sounders, battery test; detector cleaning at most every three months
Half-yearly Tower basin clean, filters, refrigerant leak check Earthing visual, cable support and glands STP performance, pump overhaul if due Smoke detector sensitivity test
Annual Chiller overhaul to OEM schedule, tube cleaning, safety controls, efficiency test Transformer oil test, relay and breaker test, earthing resistance, UPS capacity Tank and sump cleaning to state rules, consent renewal, effluent testing Functional test of every detector and call point, mains-disconnect test, general alarm

The fire row is not invented. IS 2189:2026, the fifth revision published in March 2026, sets the user’s daily and weekly checks, the quarterly test of trigger devices and sounders, detector cleaning at least every three months, a twice-yearly sensitivity test and a yearly functional test of every detector and call point (clauses 7.4, 7.5 and Table 4). It also requires written notice to the owner within 24 hours where a deficiency is not fixed at the end of testing, which is a useful contract hook: if the provider finds a fault and says nothing, the standard says it should have.

One caution on the same standard. IS 2189 is a code of practice, and no quality control order makes it compulsory on its own; it binds where a state rule, a fire NOC condition or a contract names it. That is why the next section matters.

What the law tests on its own schedule

Statutory inspection is the part of hard services that cannot be delegated by contract. You can appoint someone to arrange it, hold the file and attend the visit. You cannot appoint someone to carry your liability as occupier.

Asset Governing instrument What the buyer must hold Who performs it
Lifts and escalators State lift Acts, for example the Maharashtra Lifts, Escalators and Moving Walks Act, 2017 (retrieved 4 November 2026); hoists and lifts are item 8 of the OSH Code’s Second Schedule A current licence or inspection certificate per lift, renewed annually The state electrical inspectorate or a licensed agency, by state
Lifting machines and tackle OSH Code, 2020, Second Schedule item 9; OSH (Central) Rules, 2026 or state rules Examination reports by a competent person A competent person under the applicable rules
Pressure plant and vessels OSH Code, 2020, Second Schedule item 11; state OSH rules Test and examination records held for the life of the asset A competent person
Boilers Boilers Act, 1923 (retrieved 4 November 2026), section 8; Indian Boiler Regulations A valid registration and a current certificate to use The Inspector of Boilers
Electrical installation CEA (Measures Relating to Safety and Electric Supply) Regulations, 2023 (retrieved 4 November 2026), regulations 32 and 45 Periodic inspection reports; approval before a capacity change The electrical inspector; work by a licensed contractor
Fire systems State fire Acts and NOC conditions. In Maharashtra, a fire safety certificate (Form B) from a licensed agency under the 2006 Act (retrieved 4 November 2026), submitted twice a year in January and July The NOC, its renewal, and the periodic certificates A licensed agency, plus the fire service
Sewage and trade effluent Water (Prevention and Control of Pollution) Act, 1974; state board consent A consent to operate, with monitoring against its conditions A recognised laboratory, plus the operator
Refrigerant ODS (Regulation and Control) Rules, 2000; the HCFC phase-out plan Cylinder records, service logs, leak checks Trained technicians; reclaim or destroy, never vent

Two changes make this table look different from the one a 2019 contract was written against. The OSH Code, in force from 21 November 2025, repealed the Factories Act and moved the detail for lifts, lifting tackle and pressure plant into standards and state rules. And the building code itself changed: the National Building Code of India 2016 was withdrawn on 30 April 2026 and replaced by SP 7:2026, whose fire-safety provisions are advisory rather than mandatory (Times of India, 30 April 2026). The practical effect is that the state fire rule and your NOC conditions carry more weight, not less.

That is the reason to keep a statutory register on the same page as the plant list. A provider can hold the calendar, the appointments and the file. The expiry date remains yours.

Licensed people, not just technicians

An AMC is a promise about people, and the people need documents.

Work Who may do it Document to ask for
Electrical work on the installation A licensed wireman or supervisor of the state licensing board Licence number, and the contractor’s licence
Inspection and testing The competent person defined in the CEA regulations Appointment or authorisation, and the test report
Boiler operation A certified operator under the Boilers Act and IBR Operator certificate, matched to the boiler class
Lift maintenance OEM or OEM-authorised mechanic; state-licensed where the state requires Authorisation letter and the service mechanic’s card
Refrigerant handling A trained technician under the ODS Rules regime Training record, plus the cylinder and recovery log
Confined space, work at height, LOTO A permitted person under a written procedure Permit, training record and the rescue plan

The verification standard is the same one you would apply to a guard or a housekeeping supervisor, covered in the employee verification guide: identity, qualification, and a record that is checked rather than filed. Contractors’ staff are contract labour, and the principal employer’s duties travel with them, as the contract labour compliance guide sets out.

Spares: where “comprehensive” stops

Every comprehensive AMC has an exclusion list, and the list is the real contract. These appear on it most often: compressors and their overhaul; condenser and evaporator coils; VFDs, control boards and PCBs; motors above a stated rating; transformers and switchgear; pumps and rewinding; refrigerant gas and recovery; BMS and ELV controllers; lift ropes, sheaves and door operators; and all civil work.

There are three honest ways to handle the gap. A spares cap sets a rupee ceiling per year, per asset class. A percentage of asset replacement value puts a provision in the fee, typically 1.5% to 3% a year, and is the most predictable. A pass-through at cost plus handling keeps the buyer’s risk but removes the argument about the price of a part.

Two details decide whether any of them works. Lead time: an imported chiller controller can take six to twelve weeks, so a cap without a critical-spares list simply moves the outage. Ownership at exit: if spares were bought through the contract, the inventory, its value and its condition belong in the handover schedule, or it walks out with the provider.

A short critical-spares list is unglamorous and cheap: AHU belts and filters in the sizes actually used, pump mechanical seals, contactors and fuses for the main boards, fire panel batteries, one spare domestic water pump, and the chiller’s safety controls. The statutory compliance calendar is a useful cross-check, because the parts that fail are often the parts an inspection is about to test.

How a hard-services contract is priced

The build-up has six lines, and only one is a wage bill. The FM cost guide works through the labour half, including why a round-the-clock post needs about four people; this is what the rest looks like.

Line What drives it
Roster and statutory Posts by shift and skill, relief cover, PF, ESI, bonus, gratuity, professional tax
Preventive labour Task hours from the PPM calendar, not a percentage of the wage bill
Spares provision Criticality, asset age and the exclusion list
Specialist subcontracts OEM overhaul, lift maintenance, water treatment, thermography, testing
Consumables Filters, belts, chemicals, lamps, small tools
Service charge Supervision, planning, reporting, margin and the risk carried

One worked example, with illustrative numbers: a 1,20,000 sq ft office on a six-day week, two 250 TR water-cooled chillers, two 500 kVA transformers, two 500 kVA DG sets, four lifts, a 100 KLD sewage treatment plant, and one operator seat covered around the clock.

Line Basis Monthly
Shift operators 4 people for one 24×7 seat × ₹26,000 ₹1,04,000
Day technicians 2 × ₹30,000 plus 4% relief ₹62,400
Supervision Half a supervisor at ₹50,000 ₹25,000
Statutory on the above About 22% of wages ₹42,100
Spares provision 2% of ₹3.5 crore asset replacement value ₹58,300
Lift maintenance 4 lifts at ₹18,000 a year ₹6,000
Chiller overhaul ₹1,20,000 a year, accrued monthly ₹10,000
Water treatment and testing Chemicals, panels, third-party tests ₹13,000
Consumables Filters, belts, small parts ₹12,000
Subtotal Delivered cost before margin ₹3,32,800
Service charge 10% of subtotal ₹33,280
Monthly value Before GST at the rate in force ₹3,66,080

Read three things off it. The roster and its statutory load are 64% of the value, which is why a hard-services contract still behaves like a labour contract at the bottom. The spares provision is 16%, and without it the same quote would be about ₹3.02 lakh, 17% lower, which is exactly the gap that becomes a dispute when the first compressor goes. And the plant list made the arithmetic possible: the ₹3.5 crore replacement value is an estimate a buyer can check, and the 2% is a policy choice, not a market rate.

At ₹3.05 per square foot a month the number is plausible for this building. It is not a benchmark: the same area with air-cooled chillers, no STP and two lifts is a different building.

Measuring a hard-services contract

Soft-service scorecards count completed tasks. Hard-service scorecards need three kinds of number, and the SLA guide explains why only two of them belong in a contract with money attached.

Leading indicator. PPM compliance: tasks due, tasks done, and tasks done with a measurement and a signature. This is the only measure that tells you next month’s breakdowns. A completion rate above 95% with no readings attached is a filing statistic.

Outcome measures. Availability of tier A assets, mean time between failures, mean time to repair, and first-time fix — per asset class, because averaging a chiller with a fan coil produces a number nobody can act on.

The ratio that matters most. Planned to unplanned work. A mature plant runs near 80:20; a plant in decline drifts towards 50:50, and the drift shows up a year before the capital budget does.

Three anti-gaming patterns to watch. A work order closed the day it was raised, with no reading recorded. A chiller “restored” by resetting the alarm and leaving the approach where it was. A fire panel left in bypass while a replacement is “in process”, which is exactly the deficiency IS 2189:2026 requires to be reported in writing.

Energy: the number that pays for the contract

Chillers consume more than 40% of the energy used in commercial buildings, according to the Ministry of Power’s 2018 labelling launch. That makes the plant the only place in a facility where a maintenance decision can pay for the whole contract.

The arithmetic is simple enough to run on a napkin. A tenth of a kilowatt per tonne of refrigeration on a 500 TR plant is 50 kW. Run 4,000 hours a year and that is 2,00,000 units; at ₹8 a unit it is ₹16 lakh a year, more than twice the spares provision in the example above.

The number moves in four places:

  • Condenser approach. Fouled tubes and a dirty tower raise the condensing temperature; each degree costs roughly 2% to 3% of chiller efficiency, and the figure sits in a daily log nobody trends.
  • Water treatment. Scale and biological growth do the same thing more slowly, and the fix is a chemical programme with a monthly panel, not a brush once a year.
  • Air-side resistance. A loaded AHU filter and a dirty coil move fan energy up and cooling down; differential pressure says when, if anyone records it.
  • Setpoints and sequencing. A chilled water setpoint lowered “to make it colder” and two chillers running when one would do are control problems, not equipment problems.

Valves and insulation belong on the same list: a passing valve or bare pipe is paid for every hour the plant runs.

Two policy instruments sit behind the engineering. The Energy Conservation Building Code (retrieved 4 November 2026) applies to commercial buildings with a connected load of 100 kW or more, or a contract demand of 120 kVA or more, and sets the design baseline for HVAC and electrical systems. And since 1 January 2024 water-cooled and air-cooled chillers have been in BEE’s mandatory star-labelling regime, with efficiency tested to IS 16590 — a printed number a buyer can hold a maintenance provider to, and a way to test whether a proposed overhaul is worth doing.

Refrigerant is the slow-moving decision

An R-22 chiller is not illegal to run. It is increasingly expensive to keep running. India stopped using HCFCs in the manufacture of new equipment from 1 January 2025, completing the manufacturing phase-out under its HCFC phase-out plan (Mongabay India, 17 January 2025), while consumption steps down to a 67.5% cut in 2025 and a full phase-out in 2030, leaving a shrinking servicing allowance (Ozone Cell, control schedule, retrieved 4 November 2026)).

For a building, that is three questions at the next overhaul, not at the next breakdown. What refrigerant is in the machine, and is it still available at a sane price? Is a retrofit sensible on this asset? And what is the replacement year, given that the HFC phase-down under the Kigali Amendment, which India ratified in 2021, will move the next generation of equipment again — a direction the Environment Ministry has already signalled by telling clearance authorities to account for HFC production limits (office memorandum, 1 April 2026)?

A maintenance contract should carry a refrigerant register: what is in each machine, how much was added and when, and what the leak rate implies. A plant that needs gas every quarter has a leak, and a leak is a capital decision arriving early.

Mobilisation: the first 30 days

Most hard-service failures are inherited, and the first month decides whether you inherit them or buy them.

Week one: verify the register against nameplates, photograph every asset, and record the condition you actually find. Collect the statutory file — lift licences, boiler certificate, fire NOC and Form B equivalents, consent to operate, last inspection reports.

Week two: set criticality tiers, build the PPM calendar from the task list, agree who is on call for each tier, and confirm isolation and permit rules before anyone touches a panel.

Week three: map the specialist subcontracts — OEM, lift, fire, water treatment, testing laboratories — and confirm warranty status and what the OEM will not release.

Week four: publish the baseline — availability, PPM completion, open defects with a cost to cure and a responsible party, and the statutory expiry calendar. The mobilisation and governance page sets out the sequence.

The most valuable document from that month is a signed defect register. Without it, every pre-existing fault becomes a debate about whether it happened on your watch, and the argument is usually settled by whoever has better photographs.

Clauses worth writing

  • The asset register as a schedule, with criticality tiers and response clocks attached.
  • The PPM task list and its evidence standard: date, person, measurement, signature. A task without a measurement is a visit.
  • The exclusion list in full, plus one of the three spares mechanisms, named.
  • A critical-spares list, with quantities, storage location and ownership of the stock.
  • The statutory calendar, naming who arranges each inspection, who attends, and who holds the certificate.
  • Licence evidence on request for every technician who works unsupervised, within a stated time.
  • The OEM interface: who calls, who pays, and what happens when only the OEM can fix it.
  • Energy reporting: monthly kW per TR and specific energy, as a trend rather than a single month.
  • Exit and handover: records for the asset’s life, spares inventory, warranty documents, and an agreed condition report.

Where these contracts fail

The register is a guess. A provider prices a plant list assembled from memory, finds two extra pumps and a dead standby alternator in month one, and recovers the difference through variations for the rest of the term.

“Comprehensive” was never defined. No cap, no exclusion list, no named parts. The first compressor produces a conversation about good faith, which both sides lose.

The statutory file is empty. The lift licence expired in March, the Form B was never filed, and the fire panel has been in bypass since a detector failed. None of this is a maintenance problem; all of it lands on the maintenance provider.

The PPM is a paper exercise. Tasks are closed in a batch on the last working day, with no readings. The plant then fails in the way the skipped measurement would have predicted.

Nobody owns energy. The chiller runs three degrees above its commissioning approach, the invoice is paid, and the saving that would have funded the contract is spent on units nobody reads.

Frequently asked questions

Is technical maintenance the same as an AMC?

An AMC is one way to buy technical maintenance, and the least precise name for it. A technical maintenance contract should state the assets, the preventive task list, the spares position, the statutory calendar and the response clocks. An AMC that states only a price per asset per year is a starting point, not a scope.

What does a comprehensive AMC usually exclude?

Compressors and their overhaul, coils, control boards and drives, motors above a rating, transformers, pumps, refrigerant gas, BMS and ELV controllers, lift ropes and door operators, and all civil work. The list varies, which is why the exclusion schedule, the spares cap and the critical-spares list matter more than the headline word.

Do we still need our own electrician if we have an AMC?

You need a licensed person for the work the contract does not cover: small power changes, new points, tenant fit-outs, and anything on a live board. Many contracts also require the buyer to provide a licensed electrical contractor for statutory work. Decide which of the two you are keeping before you sign, because it changes the roster and the price.

Who is responsible for lift and fire inspections, us or the provider?

The occupier remains responsible. The provider can arrange the inspection, attend it and hold the file, and a well-written contract makes that an obligation with a date. The certificate, the licence and the consequences of an expired one stay with you.

How often should HVAC equipment be serviced?

Monthly for filters, belts, drains and water quality; quarterly for water treatment and controls; annually for the chiller overhaul, tube cleaning and safety controls, following the OEM schedule. The daily log is what makes the rest useful, because it is the only record that shows a trend rather than a visit.

The bottom line

Hard services are priced on a plant list you should be able to read, tested on a statutory calendar you cannot transfer, and judged on a preventive record that either has measurements in it or does not. Get the register, the exclusion list and the critical-spares list right, and the rest of the contract has something to stand on.

Send us your plant list, the last three months of maintenance invoices and your statutory expiry dates. We will tell you which assets are unowned, which inspections are at risk, and what the spares line should be before the next breakdown decides it for you.



Send the requirement

If this post points at a decision you are close to making, send us the scope — sites, roles and shifts — and we will confirm the licence, supervision and commercial position for your situation.

Discuss your requirement