Skip to content

Contractor agreement template for Indian works and manpower

No Indian statute prescribes the contents of a contractor agreement. What the law does is make the agreement the place where you prove the contractor’s statutory position before you pay an invoice — the licence under s.47 of the OSHWC Code, 2020, the PSARA licence where guards are supplied, the PF and ESI registrations, the GST charge, the TDS deduction and, for construction work, the BOCW cess. A contract that omits those clauses leaves you holding the liability.

Mandatory contents, and where each one sits in the template

Section titled “Mandatory contents, and where each one sits in the template”
  1. Parties, and the establishment registration numbers. Yours under s.3 of the OSHWC Code.
  2. Scope of work, and whether the activity is core or non-core under s.2(p). This decides whether s.57 applies at all.
  3. Contract labour licence, with the number of workers it permits, where the Chapter applies — s.47.
  4. PSARA licence, where the service is guarding. Private Security Agencies (Regulation) Act, 2005, s.4.
  5. PF and ESI registrations, with the UAN and insurance numbers, and the monthly challans as a payment condition — Code on Social Security, 2020, s.31(1).
  6. Wage rates, at or above the minimum wage for the state and the scheduled employment.
  7. GST at the notified rate under s.9 of the CGST Act, 2017 or s.5 of the IGST Act, 2017, and TDS under s.393(1) of the Income-tax Act, 2025.
  8. BOCW cess where the work is building or construction — 1% of the cost of construction, the rate notified under s.3(1) of the Building and Other Construction Workers’ Welfare Cess Act, 1996, which sets a range of 1 to 2%.
  9. Welfare facilities you must provide under s.53, and who provides what.
  10. Records and returns, your right to inspect, and the right of set-off for wages you pay on the contractor’s behalf under s.55(3).
  11. Insurance, injury reporting and ESI benefit claims.
  12. Termination, exit and handover.
  13. Confidentiality, personal data, governing law.
WORKS AND MANPOWER SERVICES AGREEMENT
This Agreement is made on [date] between:
(1) [Principal name], with its establishment registration number [OSHWC
registration no.] and registered office at [address] ("Principal"); and
(2) [Contractor name], a [company / firm / proprietorship] with its
establishment registration number [number] and registered office at
[address] ("Contractor").
1. SCOPE OF WORK
The Contractor shall provide [describe the service] at [site address], as set
out in Schedule 1. The activity is [core / non-core] in relation to the
Principal's establishment within the meaning of section 2(p) of the
Occupational Safety, Health and Working Conditions Code, 2020.
2. LICENCES
2.1 Where Chapter XI, Part I of the OSHWC Code, 2020 applies, the Contractor
holds contract labour licence no. [number] valid to [date] for not more than
[number] contract workers, and shall not deploy more than that number.
2.2 [Where security guards are supplied: the Contractor holds a licence under
section 4 of the Private Security Agencies (Regulation) Act, 2005, no.
[number], valid to [date], and shall deploy only guards whose character and
antecedents have been verified as the Act requires.]
2.3 The Contractor shall keep every licence and registration current, and
shall give the Principal a copy of each renewal at least [number] days before
expiry.
3. STATUTORY REGISTRATIONS AND WAGES
3.1 The Contractor shall be registered with the Employees' Provident Fund
Organisation (establishment code [code]) and the Employees' State Insurance
Corporation (code [code]), where the thresholds apply.
3.2 The Contractor shall pay every person deployed on this contract at least
the minimum wage fixed for [state] in the scheduled employment of [employment],
and shall pass on the dearness allowance revision in the month it takes effect.
3.3 Before each invoice is paid, the Contractor shall furnish the PF
electronic challan-cum-return and the ESI challan for the preceding month, and
a statement of the workers deployed with their UAN and insurance numbers. An
invoice that is not supported by them is not payable.
4. CONSIDERATION, GST AND TAX
4.1 The Principal shall pay [amount] per [month / unit], exclusive of GST, at
the rate notified for this service under section 9 of the Central Goods and
Services Tax Act, 2017, or section 5 of the Integrated Goods and Services Tax
Act, 2017 for an inter-State supply.
4.2 The Principal shall deduct tax at source under section 393(1) of the
Income-tax Act, 2025 — 1% where the payee is an individual or Hindu undivided
family and 2% in other cases — and shall issue the certificate prescribed under
that Act.
5. CESS
5.1 [Where the work is building or other construction work: the Contractor
shall pay the cess notified under section 3 of the Building and Other
Construction Workers' Welfare Cess Act, 1996, and shall furnish the receipt
before the final invoice is paid.]
6. WELFARE FACILITIES
The Principal shall provide the welfare facilities required by section 53 of
the OSHWC Code, 2020 at [site]. The Contractor shall provide [drinking water,
rest shelter, first aid, sanitary facilities] to the workers it deploys.
7. RECORDS, INSPECTION AND SET-OFF
7.1 The Contractor shall maintain the registers and records the Code requires,
and shall produce them to the Principal on demand.
7.2 If the Contractor fails to pay wages in full, or short-pays them, the
Principal may pay the shortfall to the workers and recover that amount by
deduction from any sum due under this Agreement or as a debt, as provided by
section 55(3) of the OSHWC Code, 2020.
7.3 The Contractor shall indemnify the Principal against any claim, penalty or
interest arising from the Contractor's non-compliance. This indemnity is in
addition to the right of set-off.
8. INSURANCE AND INJURY
The Contractor shall insure its liability for injury to the workers it deploys,
shall report every accident at the site to the Principal within [number] hours,
and shall cooperate in any ESI benefit claim.
9. TERM AND TERMINATION
This Agreement runs from [start date] until [end date], and may be terminated
by [number] days' written notice. The Contractor shall complete the handover of
records and shall furnish the final challans before the final payment is
released.
10. CONFIDENTIALITY AND PERSONAL DATA
Each party shall keep the other's confidential information confidential during
and after this Agreement, and shall process personal data only for the purpose
of this Agreement and with the safeguards required by the Digital Personal Data
Protection Act, 2023.
11. GOVERNING LAW
This Agreement is governed by the laws of India. The courts at [place] have
jurisdiction.
For [Principal name] For [Contractor name]
[Name, designation] [Name, designation]
Place: [place] Date: [date]
  • Guarding. Without clause 2.2 you have no evidence that your security supplier holds a PSARA licence. The licence does not cover the guard individually; the guard’s own character and antecedents verification is a separate requirement. Rule 4(9) of the Central Model Rules, 2020 also requires the licensee to commence activity within six months of the licence.
  • Construction work. Add clause 5.1, and keep the cess receipt.
  • Multi-state deployment. Name every state in clause 3.2. The minimum wage is fixed per state and per scheduled employment, and one national rate will underpay somewhere.
  • Short engagements. Keep clause 3.3 even for a one-month contract. It is the only monthly evidence you get.

Records and returns the principal employer keeps

Section titled “Records and returns the principal employer keeps”
  • Establishment registration certificate, and the contract labour licence when the Chapter applies.
  • A register of contractors, with the licence, the worker count and the deployment dates.
  • The monthly PF ECR and ESI challan for each contractor, filed against the deployment.
  • Wage registers and wage slips that reconcile to the invoices.
  • Accident reports, and the ESI claims arising from them.
  • The BOCW cess receipt and the returns where the work is construction.

Section 55(3) of the OSHWC Code makes the principal employer liable for the wages the contractor does not pay. Section 31(1) of the Code on Social Security makes the employer liable for the PF and ESI contributions on employees engaged “directly or by or through a contractor”. Both liabilities are recoverable, but only from a contractor who is still solvent. Clauses 3.3 and 7.3 are what make recovery realistic.

Stamp duty is a state subject; a works contract and a manpower supply contract may fall under different articles of your state’s stamp schedule, and the duty can be substantial on a high-value works contract. The Indian Stamp Act, 1899, s.3 charges the instruments in Schedule I, and s.35 bars an insufficiently stamped instrument from being admitted in evidence. Get the article right before signature.

Related reading: what a principal employer owes, contract labour on your site, the NDA template and EPF.