Supplier security assessment
This checklist is what you take to a supplier review. It asks twelve questions across people, access and data, and it records what evidence you accepted. Last reviewed 19 November 2026.
How to use it
Section titled “How to use it”One copy per supplier, filled in by the person who owns the contract, with our supervisor contributing the site-side rows. Score each row as met, partly met or not met, and attach the evidence. “Partly met” is a real answer and should carry a date by which it becomes met.
The checklist
Section titled “The checklist”| Requirement | What good looks like | Evidence we accept | Owner | Frequency |
|---|---|---|---|---|
| Named personnel | A current list of everyone who will work on site, with a signed substitute rule | Dated list signed by the supplier’s authorised signatory | Contract owner | Every change; reviewed monthly |
| Identity verification | Every person on site verified against a government photo ID before the first shift | Verification register with date and document type | Supplier | Monthly |
| Guard certification | Every guard and supervisor holds a Form VII certificate under rule 7 of the Central Model Rules, 2020 and a training certificate under rule 8 | Certificate copies with issue dates, checked against the roster | Supplier and our supervisor | At deployment and annually |
| Agency licence | The security agency’s state licence is valid and covers the state of the site | Licence copy with number and expiry date | Supplier | Before contract and annually |
| Subcontracting | No subcontracting without written approval, and approved subcontractors meet the same rows | Approval letter and the subcontractor’s own evidence | Contract owner | On each approval |
| Access tiers | Access is authorised per person, has a tier and an expiry, and is revoked on the last day | Signed authorisation per person; the access system listing | Site manager | Quarterly |
| Key control | One named holder per Restricted area, with a signed register | Key register with signatures and dates | Our supervisor | Monthly |
| Escorted tiers | B-tier access is actually escorted, every time | Post log of escorted entries | Our supervisor | Weekly |
| Data scope | The supplier knows what personal data it holds, why, and for how long | Data-flow note and retention schedule | Contract owner | At contract and annually |
| Access to systems | Remote access is named, logged and revocable; no shared logins | Access listing and a sample of logs | Supplier’s IT and your CISO | Quarterly |
| Audit | One audit a year against a stated scope, plus after a serious incident | Audit report with findings and closure dates | Contract owner | Annually |
| Exit readiness | Data return format, deletion confirmation, key and card recovery described and agreed | Exit checklist, dry-run once during the contract | Contract owner | Annually |
Worked failure
Section titled “Worked failure”An IT staffing supplier scored “not met” on the remote access row. Three of its engineers connected to the client’s ticketing system from a shared login, and the password had not changed in two years.
The lesson is not that the checklist is flexible. It is that an overrun written down and signed is a management decision, while an overrun nobody noticed is how a shared password survives four years.
Escalation and review
Section titled “Escalation and review”Three findings in the same section, or any finding that is still open after two reviews, goes to your CSO and the supplier’s account head in writing. Any breach involving personal data goes to your CISO the same day, because the CERT-In six-hour clock may already be running and the Data Protection Board notice under the DPDP Act, 2023 is drafted by you, not the supplier.
Review the whole checklist once a year to confirm the rows still match your contracts, and whenever a supplier’s scope changes. A checklist that has not changed while the contracts have is measuring the past.
Related
Section titled “Related”- Supplier security requirements — the clauses these rows test.
- Supply chain security risks — what each failure looks like in practice.
- Security incident reporting — the internal process a supplier’s notice feeds.
- What a guard post costs — the commercial side of a guarding review.