Business continuity plans
A continuity plan is a short document with a clear first page: who declares a disruption, who is called, and what each team does in the first hour. Everything after that page is detail. If your plan opens with a foreword, it is not written for the day it is needed.
Trigger and owner
Section titled “Trigger and owner”Write the plan once the impact analysis has produced recovery targets. The continuity lead writes it; the business owner signs it. Each critical activity gets a plan owner accountable for its procedure, and the plan is not approved until every activity in the analysis has one.
Rewrite the plan when a site, a critical system, a key supplier or a plan owner changes. Review it every year regardless, and after every exercise and every real invocation.
The steps
Section titled “The steps”| # | Step | Output | Elapsed |
|---|---|---|---|
| 1 | Set the invocation rule: who may declare, on what evidence, and who can act in their absence | A first page with names, alternates and telephone numbers | 1 day |
| 2 | Write the first-hour actions per team: people, premises, systems, customers, communications, records | Six one-page action sheets | 1 week |
| 3 | Write the recovery procedure per critical activity, to its recovery time objective | One procedure per activity, with dependencies listed | 3 weeks |
| 4 | Assemble the recovery resources: standby site, equipment, supplier commitments, manual forms, cash, keys | A resource list with quantities and where they are held | 2 weeks |
| 5 | Prepare the communication: who speaks to staff, customers, regulators and the press, and in what order | Contact tree, three message templates, a named spokesperson | 1 week |
| 6 | Exercise, then amend | Exercise report with findings and closure dates | Every quarter to every year |
The exercise ladder
Section titled “The exercise ladder”| Exercise | What happens | What it proves | Frequency |
|---|---|---|---|
| Desktop | The team talks through a scenario for 90 minutes with the plan open | That the plan is readable and the roles are understood | Twice a year |
| Walkthrough | One team walks its procedure, checks the resources exist, dials the numbers | That the contact list and the resource list are real | Once a year |
| Simulation | A scenario runs in real time for half a day, with an injects list | That decisions get made under pressure and the escalation works | Once a year |
| Full test | Standby site activated, or a system failed over, with real users | That recovery targets are achievable | Every two years, or per client contract |
A desktop exercise costs an afternoon and finds the phone numbers that no longer work.
Timings and records
Section titled “Timings and records”A plan for a mid-sized organisation takes six to eight weeks to write, and about two days a year per activity to keep current. Keep the exercise reports and the amendment log. An auditor who sees three reports with findings and closures will believe the rest; an auditor who sees none will test a procedure, and it is usually the one that fails.
Worked example
Section titled “Worked example”A 3PL warehouse operator with one site and 140 client accounts wrote its plan in seven weeks. The first page named the operations head as declarer, with the shift manager as alternate, and gave both numbers plus a landline. The first-hour sheets covered six teams, and the standby plan was unusual: the neighbouring warehouse of a friendly competitor, with 20 pallet positions available under a reciprocal arrangement confirmed in writing.
The first desktop exercise used a monsoon flood that closed the main gate. It found three things in 90 minutes: the contact tree listed a customer’s old account manager, the manual dispatch forms sat in the office the flood would close, and nobody had agreed who could authorise a move to the standby warehouse. The amendments took an afternoon. A walkthrough six months later found the standby warehouse had changed hands and the agreement had not been renewed.
What goes wrong
Section titled “What goes wrong”- Exercises with no findings. An exercise that finds nothing was a briefing, not a test.
- Contact details from a directory export. Mobiles change. Test them in a walkthrough, not in an incident.
- No manual fallback. The plan assumes a system that is down.
Related
Section titled “Related”- Critical functions and recovery targets — the numbers the plan is built to meet.
- Business continuity team — who is in the room, with the authority to act.
- Business continuity management — the scope and policy behind the plan.
- Security incident reporting — the process an incident follows before a disruption is declared.