Critical functions and recovery targets
A business impact analysis tells you which activities must resume, in what order, and how quickly. Its output is a table with one row per activity and four numbers per row: maximum tolerable downtime, recovery time objective, recovery point objective, and the minimum service level you would accept while recovering.
Who this applies to
Section titled “Who this applies to”The continuity lead, with each department head, in the first three months of a programme. Repeat it annually and whenever a contract, a site or a system changes. Do it before you sign a client contract with a service-level penalty for interruption, so the number is a decision rather than a discovery.
The four numbers
Section titled “The four numbers”| Term | Plain meaning | Who decides it |
|---|---|---|
| Maximum tolerable downtime (MTD) | The longest the activity can stop before the harm becomes unacceptable — to a customer, a regulator, a person | The business owner, not IT |
| Recovery time objective (RTO) | The time you plan to take to restore the activity, always shorter than the MTD | The continuity lead, funded by the owner |
| Recovery point objective (RPO) | How much data you can afford to lose, expressed as time — one hour of transactions, one day of dispatch records | The business owner with IT |
| Minimum service level | What you would deliver while recovering: half the lines, manual dispatch notes, two of five counters | The business owner |
The method
Section titled “The method”- List activities, not departments. “Dispatch paperwork”, “inbound quality check”, “invoicing”, “customer helpline”, “site guarding” — things with a start and a finish.
- Ask the harm question for each. What happens at one hour, one day, three days, one week? The point where the answer changes from inconvenience to unacceptable is the MTD.
- Rank dependencies. People, systems, suppliers, premises, and the paperwork that must exist in a drawer.
- Set the targets. RTO below MTD, with margin. Write down what the recovery assumes, because that assumption is what the exercise will test.
- Cost the gap. For every activity where the current capability is worse than the target, record the gap and the fix, with a price. The BIA’s job is to make that list short and specific.
- Get it signed. Department heads sign their own rows. An unsigned row will be renegotiated during the disruption.
How we apply it
Section titled “How we apply it”We run the site-side rows, the ones organisations forget: which posts stay staffed when a building is unusable, how long a standby location can run on temporary guarding, and what happens to access control when the card system is part of the outage. The rows those numbers come from are on critical functions and recovery targets; the plan that uses them is in business continuity plans.
Worked example
Section titled “Worked example”A 500-bed hospital runs the analysis for six activities. Three rows, as signed:
| Activity | Harm at 1 hour | Harm at 1 day | MTD | RTO | RPO | Minimum service level |
|---|---|---|---|---|---|---|
| Emergency department intake | Ambulances diverted, risk to life | Regional impact, regulatory notice | 0 | 0 (never stops) | Not applicable | Manual registration on paper, two triage rooms on generator |
| Operation theatre schedule | Cases delayed | Elective list lost for a week | 4 hours | 2 hours | 15 minutes of scheduling data | Two of six theatres, trauma cases only |
| Pharmacy dispensing | Ward stock covers 6 hours | Stock-out on 20 lines | 6 hours | 4 hours | 1 hour of dispensing records | Manual indent, ward stock, emergency formulary |
The numbers did three things. They made the generator test the most important exercise in the hospital, because two rows depended on it. They showed the pharmacy’s six-hour window rested on ward stock nobody had counted in a year. And they made the theatre row defensible: two of six theatres was the medical superintendent’s decision, not an IT assumption.
Common failures
Section titled “Common failures”- Departments marking everything critical. If 40 activities are critical, none is. Force the ranking: what stops first, and what can wait a week.
- No minimum service level. Recovery becomes all-or-nothing, so the business stops for a week instead of running at half.
- RTO set to what IT can deliver today. The target should follow the harm, then the gap gets costed. Set it the other way round and the BIA becomes a description.
Related
Section titled “Related”- Business continuity management — the programme these numbers sit in.
- Business continuity plans — turning targets into procedures and exercises.
- Business continuity team — who executes the recovery.
- Security risk assessment — the likelihood and impact method, which shares its scoring with this one.