Site security plan
A site security plan converts a risk register into posts, shifts, procedures and records for one address. It is triggered by a new site, a layout change, a contract renewal or a serious incident, and it is not finished until your CSO has signed the post list and the roster matches it.
Trigger and owner
Section titled “Trigger and owner”The plan starts when one of four things happens:
- A new site is leased or a floor is added.
- The layout changes in a way that alters an entry route, a perimeter or a storage location.
- The guarding or housekeeping contract is renewed or re-tendered.
- An incident shows that the current arrangement did not work.
Your CSO or site head owns the plan and signs it. We survey the site, draft the plan and cost the posts. The plan is not valid until it is signed, and the roster is not valid until it matches the signed post list.
The steps
Section titled “The steps”| # | Step | Who does it | Output | Elapsed |
|---|---|---|---|---|
| 1 | Site survey: entrances, perimeter, blind spots, storage, utilities, neighbouring tenants, police response route | We survey with your facilities team | Survey note with photographs and a sketch | 1–2 days |
| 2 | Risk assessment against the site baseline | Your CSO with our input | Scored risk register for this site | 3–5 days |
| 3 | Post list: every post, its location, hours, duties and shift pattern | We draft, your CSO approves | Post list with a relief calculation | 2 days |
| 4 | Procedures: entry and exit, visitor handling, key control, patrol rounds, escalation, registers | We draft against your policy | Post orders per post | 3–5 days |
| 5 | Sign-off and mobilisation: vetting check, briefing, handover against the plan | Your CSO signs; we mobilise | Signed plan, roster, briefing record | 2–4 weeks |
Step 3 is where most plans fail, because a post list without a relief calculation produces a roster that cannot be worked. The arithmetic is simple and worth doing in front of the client.
A post that must be manned 24 hours a day, seven days a week, needs 21 shift-days a week at eight-hour shifts. A guard on a six-day week delivers six shift-days. That gives 3.5 guards before you account for festival leave, sickness and attrition. In practice you staff 4.2 to 4.5 guards per round-the-clock post. A plan that lists “one guard at the gate, 24×7” and budgets one guard is a plan for a shortage.
Timings and records
Section titled “Timings and records”| Record | Kept by | Where | Retention |
|---|---|---|---|
| Signed site security plan | Your CSO | Your document system, copy with us | Life of the contract plus the period your policy sets |
| Post list and roster | Our supervisor | Site file and your shared folder | 12 months minimum |
| Attendance sheet, signed per shift | Our supervisor | Site file | 12 months minimum |
| Visitor and key registers | The post | Site file | As your policy and the DPDP Act, 2023 require |
| Inspection and post-check reports | Our field officer | Reporting system | 12 months |
| Incident reports | Your CSO and our account owner | Both | As your policy requires |
The plan itself should name the review date. A plan reviewed only when something breaks is a plan that has stopped being read.
Worked example
Section titled “Worked example”A 1.2 lakh sq ft distribution centre near Bengaluru: one main gate, one emergency gate, a loading bay with six docks, a bonded store and an office block for 40 staff. Twenty-four contract loaders a day during season, 60 own staff. The client’s risk register scores theft from the loading bay at 5 (severe) and unauthorised entry at the emergency gate at 4 (major).
The approved post list:
| Post | Location | Hours | Shifts | Duty |
|---|---|---|---|---|
| P1 | Main gate | 24×7 | 3 | Vehicle and person entry, visitor register, gate pass check |
| P2 | Loading bay | 06:00–22:00 | 2 | Dock allocation, seal check, outbound load verification |
| P3 | Emergency gate | 24×7 | 3 | Locked post; opens for fire evacuation only, alarm-linked |
| P4 | Yard and perimeter patrol | 20:00–06:00 | 1 | Four rounds a night, checkpoint tags at six points |
| P5 | CCTV and alarm monitoring | 24×7 | 3 | Screen watch, alarm response, radio coordination |
That is five posts, 12 shift-posts a day, 84 shift-posts a week. At 4.3 guards per round-the-clock post for P1, P3 and P5, three for the two-shift loading bay and two for the night patrol, the roster needs 18 guards and three supervisors. The client’s previous plan carried the same 18 guards, spread differently and with no monitoring post, which is why the loading bay scored 5.
Two design decisions came out of the survey and cost nothing. The emergency gate was rehung to open outward and fitted with a break-glass alarm instead of a padlock, so it remains a fire route without a key holder on site. The dock office window was moved 2 metres so that the P2 guard can see the fifth and sixth docks without leaving the post.
Timings in practice
Section titled “Timings in practice”Survey to a signed plan is usually two to three weeks for a site this size. Mobilisation adds two to four weeks, most of it waiting on character and antecedents verification reports under rule 7(4) of the Private Security Agencies Central Model Rules, 2020, which the police must issue within 15 days of receiving the form. Start the clock before you need the guards.
What goes wrong
Section titled “What goes wrong”- No relief factor. The roster covers 21 shift-posts a week with 18 guards and the gap is filled by double shifts. Fatigue shows up as sleeping on post within three months.
- Procedures written for a different site. A plan copied from another plant keeps a vehicle search at a site with no vehicles and drops the dock check at a site that needs it.
- Registers nobody audits. A visitor register with three consecutive days in the same handwriting is a register written up after the fact.
- The plan lives with the vendor. If the client cannot produce the signed plan, there is nothing to measure the vendor against. Hold your own copy.
- No exit clause. The plan should say who returns the keys, the registers and the footage at the end of the contract, and by when.
Related
Section titled “Related”- Security risk assessment — step 2 in detail, with a filled register row.
- Physical security measures — the control set the plan draws on.
- Security guards — vetting, training and shift rules.
- How a site security plan is built — the narrative version.
- Site security deployment and supervision — the posts and supervision behind a signed plan.